MSC CONTAINER TERMINAL - ENTRONCAMENTO, SETTLEMENT OF BALLAST TRACK AND SLAB TRACK

The Terminal beginning at REFER SA’s Material Park in an extension of 400 mlv
connects, by means of an AMV, the three lines which serve the Container Terminal.

Railway Terminal consisting of three lines interconnected by line switch devices
(AMV) in a 1,514 ml extension.

Two lines (LII and LIII) built in slab track with two AMV in an extension of 591 mlv
and one line (LI) with approximately 923 mlv in ballast track with two AMV.

Installation of bumpers on line I and line III.

FACTS

Client
OPWAY, S.A.

Owner

MSC - Terminal do Entroncamento,  S.A.

Location

Entroncamento - Riachos

Execution deadline
4 months

Material applied
Rail used UIC 54Kg – 3.028 ml
Double-block sleepers used – 5.000 un.
Line switch devices Tg. 0,11 - 4un.
Fixed bumpers Rawie – 2 un.
Ballast – 4.000 Ton.
Thermal Welding Kits UIC 54Kg – 208 un.

Equipment used

Rail-Route – 2 un.
Backacter shovel – 1 un.
Tamping machine – 1 un.
Grader – 1 un.

Track light equipment:
- Moto – Joints,
- Moto - Rail,
- Sleeper-screw driver,
- drilling machine,
- Rail jacks,
- Graders
 

   